Florida Public Service Commission

FLORIDA PUBLIC SERVICE COMMISSION
SUMMARY OF ORDERS ISSUED
WEEK OF NOVEMBER 20 - 24, 2017

ELECTRIC INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20150171-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Petition for issuance of nuclear asset-recovery financing order, by Duke Energy Florida, Inc. d/b/a Duke Energy.
20170001-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Fuel and purchased power cost recovery clause with generating performance incentive factor.
20170183-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Application for limited proceeding to approve 2017 second revised and restated settlement agreement, including certain rate adjustments, by Duke Energy Florida, LLC.
20170208-EI 11/20/2017 PSC-2017-0452-FOF-EI
Final Order PSC-2017-0452-FOF-EI granting GPC approval for authority to issue and sell securities and receive common equity contributions; GPC shall file a consummation report within 90 days of the end of the fiscal year; docket to remain open until staff's review of consummation report; docket to be closed administratively.
Application for authority to issue and sell securities and to receive common equity contributions during 12 months ending December 31, 2018, pursuant to Chapter 25-8, F.A.C., and Section 366.04, F.S., by Gulf Power Company.
20170002-EG 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Energy conservation cost recovery clause.
20170175-EU 11/22/2017 PSC-2017-0455-CO-EU
Consummating order PSC-2017-0455-CO-EU makes Order PSC-2017-0414-PAA-EU effective and final; docket to be closed.
Joint petition for approval of amended territorial agreement in Orange and Osceola Counties, by Duke Energy Florida, LLC and Reedy Creek Improvement District.
20170169-EI 11/20/2017 PSC-2017-0449-PAA-EI
PAA Order PSC-2017-0449-PAA-EI approving negotiated renewable energy contract between GPC and Bay County; utility shall be permitted to petition for recovery of costs associated with the negotiated renewable energy contract through the fuel and purchased power recovery clause; any proceeds received as a result of selling Renewable Energy Credits shall go to the benefit of the ratepayers; if no protest, order shall become final and effective upon the issuance of CO; docket to be close if order becomes final; protest due 12/11/17.
Petition of Gulf Power Company for approval of negotiated renewable energy power purchase agreement with Bay County, Florida.
20100437-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Examination of the outage and replacement fuel/power costs associated with the CR3 steam generator replacement project, by Progress Energy Florida, Inc.
20170009-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Nuclear cost recovery clause.
20170009-EI 11/20/2017 PSC-2017-0451-AS-EU
Final Order PSC-2017-0451-AS-EU approving Duke Energy’s petition for the 2017 revised and restated settlement agreement and all matters contained in attached exhibits; approving new and revised tariff sheets reflecting final rates and charges; if no timely appeal, Dockets 20170183-EI and 100437-EI to be closed; Dockets 150171-EI, 20170001-EI, 20170002-EI and 20170009-EI to remain open for future disposition by Commission.
Nuclear cost recovery clause.
GAS INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20170180-GU 11/20/2017 PSC-2017-0453-PAA-GU
PAA Order PSC-2017-0453-PAA-GU approving a special contract between Chesapeake and Mosaic as shown in Attachment A effective 11/7/17; order to become final and effective upon issuance of CO; once required actions are completed, docket to be closed; protest due 12/11/17.
Petition by the Florida Division of Chesapeake Utilities Corporation for approval of special contract with Mosaic Fertilizer LLC.
20170189-GU 11/22/2017 PSC-2017-0454-TRF-GU
Order PSC-2017-0454-TRF-GU approving FCG’s petition for approval of safe true-up and associated cost recovery factors, effective 1/18; if no protest, order to become final and effective upon issuance of CO; if order becomes final, docket to be closed; protest due 12/13/17.
Petition for approval of safety, access, and facility enhancement program (SAFE) true-up and associated cost recovery factors, by Florida City Gas.
WASTEWATER INDUSTRY
DOCKET NO. DATE FILED. ORDER NO. AND DESCRIPTION DOCKET TITLE
20130178-SU 11/20/2017 PSC-2017-0450-FOF-SU
Final Order PSC-2017-0450-FOF-SU granting Crooked Lake’s request for extension of time to complete remaining Phase II pro forma projects by 3/31/18; upon completion Crooked Lake to submit copy of final invoices and cancelled checks for remaining Phase II pro forma projects and documentation that general liability insurance is being maintained by 4/30/18; docket to remain open pending confirmation that the remaining pro forma projects and documentation have been completed; once required actions are completed, docket to be closed administratively.
Application for staff-assisted rate case in Polk County by Crooked Lake Park Sewerage Company.